MES manufacturing execution system

ERP plans what to make. MES records what actually happened on each machine, shift and batch. We build MES that operators can use with gloves on, that pulls machine signals where they exist, and that gives your quality team genealogy from raw material lot to finished pallet.

A worker operating a large industrial machine on a factory floor

Modules

Modules we build into your MES

Start with the modules that matter most and add the rest in later releases.

Work order execution
Production orders from ERP released to lines, with operation steps, routing and operator sign off at each stage.
Machine data and OEE
Run, idle and stop signals from PLCs, IoT gateways or manual entry, with downtime reasons and OEE by line and shift.
Quality checks
In-process inspection plans, sampling, SPC charts, non-conformance records and hold or release decisions.
Traceability and genealogy
Lot and serial tracking from inward material to dispatch, so a complaint can be traced to a batch, machine and operator.
Material and WIP
Material issue against orders, WIP stock between stages, scrap and rework booked where it happens.
Shift and labour
Shift handover notes, operator skills matrix and output per operator, without turning it into surveillance.
Shop floor screens
Andon boards and line displays showing target versus actual, so supervisors see problems within the hour.

AI built in

Where AI saves time in this system

  • Downtime reason clustering

    Groups free text stop reasons into usable categories and shows which ones cost the most hours.

  • Early quality warnings

    Watches process parameters and inspection results, and flags drift before a batch goes out of specification.

  • Shift summary

    Writes a plain shift report from the data: output, losses, open issues and what the next shift should watch.

  • SOP assistant

    Answers operator questions from your approved SOPs and work instructions, with a link to the source page.

Plant performance
Illustrative
OEE today
68%
First pass yield
96.2%
Downtime hours
14.5
Open NCRs
9

OEE by week (%)

OEE by week (%), point 1: 59OEE by week (%), point 2: 61OEE by week (%), point 3: 60OEE by week (%), point 4: 63OEE by week (%), point 5: 64OEE by week (%), point 6: 62OEE by week (%), point 7: 66OEE by week (%), point 8: 67OEE by week (%), point 9: 66OEE by week (%), point 10: 68

Downtime by reason

  • Changeover34
  • Breakdown26
  • Material wait18
  • Quality hold12
  • Other10

Effort and cost

USD 1,800 to 3,200

INR 1,79,100 to 3,18,400, plus taxes, for a typical first release

Effort
900 to 1,600 hours
Timeline
Pilot line in 5 to 7 weeks, plant rollout after

At the 2good.dev rate of USD 2 or INR 199 per hour, billed against outputs you accept. Your own estimate depends on modules, integrations and data migration.

Build, buy or both

Large plants on SAP often do well with SAP's own manufacturing modules or a packaged MES, provided the processes fit. For many Indian MSME and mid-size plants those products are too heavy or too costly, and Odoo's manufacturing app covers simple discrete work. Custom or hybrid pays off when your process is unusual (batch and continuous mixed, regulated pharma records, auto component traceability for OEM audits) or when the machines are a mix of old and new. We usually start with one line, prove the data is right, then roll out.

Connects with

  • SAP, Oracle or Odoo ERP
  • PLCs via OPC UA or Modbus
  • IoT gateways and SCADA
  • Weighing scales and barcode printers
  • LIMS or QC lab systems
  • Tally for smaller plants
  • Power BI or Metabase

Questions

MES: common questions

Our machines are old. Can we still have MES?

Yes. Older machines can use simple sensors or operator entry on a tablet. We mix automatic and manual capture and show which is which.

Does it replace our ERP?

No. ERP keeps planning, inventory value and accounts. MES handles execution and sends confirmations, consumption and output back.

Can it meet pharma record requirements?

We design for 21 CFR Part 11 and EU GMP Annex 11 expectations such as audit trails and e-signatures. Validation is done with your QA team.

Talk to us

Planning your MES?

Tell us what you use today and what is not working. We will say whether to extend it or build.

Timeline

Start a conversation

Tell us what you are trying to build.

Share the problem in a short call. You leave with a clear view of the approach, the team and the cost.

Or get a ballpark proposal in two minutes

A specialist replies within one working day. The first conversation is free.

Chat with the Code Colonies team on WhatsApp